Task: contract_milestone_pay (construction milestone payable)
Implement a contract milestone payment desk for an EPC / construction settlement. This is a business-policy pipeline (retention, late penalty, change order, tax), not an algorithms puzzle. Use integer arithmetic only. Hardcode the demo inputs below and print one integer: the final payable.
Business requirements (authoritative)
- Earned value:
earned = contract_value * progress_pct / 100. - Retention withhold:
retention = earned * retain_pct / 100(demo uses retain_pct = 5). - Net after retention:
net = earned - retention. - Late penalty: if
days_late > grace_days(grace_days = 7), setpenalty = net * late_rate / 100(late_rate = 2); otherwisepenalty = 0. Penalty is always computed fromnet, never fromearned. - After penalty:
net2 = net - penalty. - Change order:
taxed_base = net2 + change_order. Iftaxed_base < 0, settaxed_base = 0. - Tax:
tax = taxed_base * tax_rate / 100(tax_rate = 6). - Payable:
payable = taxed_base + tax. Ifpayable < min_pay(min_pay = 500), setpayable = min_pay.
Demo inputs (hardcode)
contract_value = 100000progress_pct = 40retain_pct = 5days_late = 10grace_days = 7late_rate = 2change_order = -2000tax_rate = 6min_pay = 500
Requirements
- Provide named helpers (or clear stages) for earned, retention, penalty, change+tax, and floor — not one opaque expression.
- Print only the final integer (no labels).
- Align to the business requirements above; do not invent alternate thresholds or penalty bases.
Expected output (self-check)
Exactly one line: 37354
Deliverable